Boat Launch
PROJECT INFORMATION:
Reports released from In Camera meetings of Council:
August 10 2015 - Breakwater Option Decision
February 1 2016 - Budget Update
March 7 2016 - Geogrid Textile Order
May 2 2016 - Contractor Decision
June 5 2017 - Floating Dock Construction
May 22 2018 - Boat Launch Upgrade Project Completion
Staff Reports:
April 20 2015 - Budget Resolution
April 24 2015 - Engineering Proposals
September 10 2015 - Pre-cast Concrete Panels
October 5 2015 - Lock Blocks and Freight
July 18 2016 - Phase 2 Budget Update
July 22 2018 - Boat Launch Phase 2 Complete
September 19 2016 - Boat Launch Survey Report
Construction:
Design:
Final Design - October 21 2015:
Communications:
Announcement of Construction Contract- May 2016
Announcement of Phase 2 Completion - July 2016